Question
Download Solution PDFAbhay and Bharat can complete a certain piece of work in 9 and 11 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
Abhay's time to complete work (A) = 9 days
Bharat's time to complete work (B) = 11 days
They work together for 3 days.
Formula used:
Remaining work = Total work - (Work done together in 3 days)
Time taken by A to complete remaining work = Remaining work / (Work done by A in 1 day)
Calculations:
Work done by Abhay in 1 day = 1/9
Work done by Bharat in 1 day = 1/11
Work done together in 1 day = 1/9 + 1/11
⇒ Work done together in 1 day = (11 + 9) / (9 × 11) = 20 / 99
Work done together in 3 days = 3 × (20 / 99) = 20 / 33
Remaining work = 1 - 20/33 = 13/33
Time taken by Abhay to complete remaining work = (13/33) / (1/9)
⇒ Time taken by Abhay to complete remaining work = 117 / 33
∴ The correct answer is option 1.
Last updated on Jun 19, 2025
-> The Railway Recruitment Board has released the RPF Constable 2025 Result on 19th June 2025.
-> The RRB ALP 2025 Notification has been released on the official website.
-> The Examination was held from 2nd March to 18th March 2025. Check the RPF Exam Analysis Live Updates Here.