The expected time of a PERT activity is given by: [where to = Optimistic time, tm = Most likely time, tp = Pessimistic time]

This question was previously asked in
SJVN ET Mechanical 2019 Official Paper
View all SJVN Executive Trainee Papers >

Answer (Detailed Solution Below)

Option 1 :
Free
SJVN ET General Awareness Mock Test
20 Qs. 20 Marks 12 Mins

Detailed Solution

Download Solution PDF

Concept:

The PERT (Project Evaluation and Review Technique) technique is used, when activity time estimates are stochastic in nature. For each activity, three values of time (optimistic, most likely, pessimistic) are estimated.

  • Optimistic time (to) estimate is the shortest possible time required for the completion of the activity
  • Most likely time (tm) estimate is the time required for the completion of activity under normal circumstances
  • Pessimistic time (tp) estimate is the longest possible time required for the completion of the activity


In PERT expected time of an activity is determined by using the below-given formula:

Additional Information

Variance, σ2 = 

Latest SJVN Executive Trainee Updates

Last updated on Jul 1, 2025

-> SJVN Executive Trainee Written Exam date is out, The computer based exam will be held on 10th, 11th August 2025.

->SJVN Executive Trainee recruitment 2025 application form has been released. Applicants can apply for the SJVN recruitment 2025 Executive Trainee till May 18.

->SJVN Limited has announced the recruitment notification for the position of Executive Trainee 2025.

->A total of 114 vacancies are available for the SJVN Executive Trainee Recruitment across various disciplines such as Civil, Mechanical, Electrical, Environment, Electronics & Communication, and more.

->The selection process of SJVN Executive Trainee recruitment 2025, as per the previous notification, includes a Computer-Based Test, Group Discussion, and Personal Interview.

->Once selected, candidates will be required to sign a service agreement bond of Rs. 10,00,000/- (Rs. 7,50,000/- for SC/ST/PWD candidates), committing to complete the prescribed training and serve the company for a minimum of 3 years.

->Candidates must refer to the SJVN Executive Trainee Previous Year Papers and boost their preparation for the exam.

More Operations Research Questions

Hot Links: teen patti gold old version teen patti 51 bonus teen patti master list