Statement (I): The critical path has been defined as the longest duration path between the first and the last nodes of a project.

Statement (II): The duration of a project is not always the same as the duration of its critical path.

Statement (III): The Earliest start and finish times of an activity are based on the condition that every activity will not be started and finished as early as possible.

Find the correct code for given statements being correct or incorrect.

This question was previously asked in
UGC NET Paper 2: Management July 2018
View all UGC NET Papers >
  1. Statement (I) and (II) are correct but (III) is not correct.
  2. Statement (I) and (III) are correct but (II) is not correct.
  3. Statement (I) is correct but (II) and (III) are not correct.
  4. Statement (II) is correct but (I) and (III) are not correct.

Answer (Detailed Solution Below)

Option 3 : Statement (I) is correct but (II) and (III) are not correct.
Free
UGC NET Paper 1: Held on 21st August 2024 Shift 1
50 Qs. 100 Marks 60 Mins

Detailed Solution

Download Solution PDF

The correct answer is Statement (I) is correct but (II) and (III) are not correct.

Critical Path Method (CPM):

  • The Critical Path Method (CPM) is a network analysis approach.
  • It finds out which sequence of activities has the least measure of scheduling resilience by which it predicts the duration of the project.
  • It is based on the estimation of the standard time needed for the execution of an activity.

Key Points

  •  The critical path is the longest path time-wise which can be determined from the forward path method only.
  • The critical path is the longest path through the network and time along this path gives the project duration.
  • The critical path joins those activities which are critical.
  • Thus Statement I is correct. 
  • The critical path (or paths) is the longest path (in time) from Start to Finish; it indicates the minimum time necessary to complete the entire project.
  • The duration of a project is the same as the duration of its critical path.
  • Thus Statement II is not correct. 
  • The early start time refers to the time at which all activities start as early as possible.
  • The early finish time refers to the time at which all activities finish as early as possible. 
  • The Earliest start and finish times of activity are based on the condition that every activity will be started and finished as early as possible.
  • Thus Statement III is not correct. 

Hence, the correct answer is Statement (I) is correct but (II) and (III) are not correct.

Latest UGC NET Updates

Last updated on Jul 7, 2025

-> The UGC NET Answer Key 2025 June was released on the official website ugcnet.nta.ac.in on 06th July 2025.

-> The UGC NET June 2025 exam will be conducted from 25th to 29th June 2025.

-> The UGC-NET exam takes place for 85 subjects, to determine the eligibility for 'Junior Research Fellowship’ and ‘Assistant Professor’ posts, as well as for PhD. admissions.

-> The exam is conducted bi-annually - in June and December cycles.

-> The exam comprises two papers - Paper I and Paper II. Paper I consists of 50 questions and Paper II consists of 100 questions. 

-> The candidates who are preparing for the exam can check the UGC NET Previous Year Papers and UGC NET Test Series to boost their preparations.

Hot Links: teen patti gold teen patti party teen patti palace real cash teen patti teen patti club