Critical Path Method (CPM) network is

This question was previously asked in
APSC JE Civil 14 Jul 2024 Official Paper
View all APSC JE Papers >
  1. event oriented
  2. activity oriented
  3. slack oriented
  4. float oriented

Answer (Detailed Solution Below)

Option 2 : activity oriented
Free
APSC JE Civil Surveying Mock Test
0.7 K Users
20 Questions 20 Marks 25 Mins

Detailed Solution

Download Solution PDF

Explanation:

Critical Path Method (CPM) Network

The Critical Path Method (CPM) is a project management technique used to schedule project activities. It focuses on identifying the longest sequence of dependent activities, known as the critical path, to determine the project duration. CPM is widely used in construction, manufacturing, and other industries for effective project planning and monitoring.

Analyzing the Given Options

  1. Option 1: "Event oriented"

    • Event orientation is a characteristic of the Program Evaluation and Review Technique (PERT), not CPM.

    • PERT focuses on milestones (events) rather than activities, making this option incorrect for CPM.

  2. Option 2: "Activity oriented" (Correct Answer)

    • CPM is activity-oriented, meaning it focuses on the sequence and duration of activities required to complete the project.

    • It emphasizes scheduling and resource allocation for each activity, making this the correct answer.

  3. Option 3: "Slack oriented"

    • Slack refers to the amount of time an activity can be delayed without affecting the project schedule.

    • While CPM calculates slack, it is not the primary focus, making this option incorrect.

  4. Option 4: "Float oriented"

    • Float (or total float) is the amount of time a task can be delayed without delaying the project.

    • Similar to slack, while float is calculated in CPM, the method is not primarily float-oriented, making this option incorrect.

  5. Option 5: "Not applicable"

    • This option is unrelated to the characteristics of CPM and is therefore incorrect.

Latest APSC JE Updates

Last updated on Jul 12, 2025

-> APSC JE recruitment 2025 notification released under the Soil Conservation Department. Candidates can apply for the recruitment from July 16 to August 15 (26/2025).

-> APSC JE Admit Card 2025 is released on 11th July 2025. Candidates who have applied for APSC JE can download their admit card from official website.

-> For the Adv 05/2025, the APSC JE Civil Exam date 2025 has been released. As per the new schedule, the exam will be conducted on July 20.

->APSC JE recruitment 2025 notification released for Mechanical Engineering.

->A total of 17 vacancies are announced for the Water Resource Department under Adv. No, 18/2025.

->APSC JE final result for Adv. No. 10/2024 has been released in PDF. 

->APSC JE Civil Engineer recruitment notification has been released for the Fishery Department. 

->Applicants can fill the APSC JE application form for Civil Engineer, Fishery Department from May 3. A total of 32 vacancies have been announced. 

->APSC JE 2025 document verification schedule released (10/2024).

-> The APSC JE Notification 2025 has been released for 650 vacancies of AE Civil under the Public Works Roads Department (PWRD) & Public Works (Building & NH) Department. 

-> The recruitment is also ongoing for 80 vacancies of Advt. No. 10/2024. For the same, the Screening Test (OMR Based) was held on 22nd December 2024.

-> Candidates with an Engineering Diploma are eligible for this post.

-> Prepare for the exam using APSC JE Test Series and APSC JE Previous Year Papers.

Get Free Access Now
Hot Links: teen patti rules teen patti flush teen patti yes teen patti master game teen patti yas