Question
Download Solution PDF4 men’s work is equal to 6 women’s work, and 4 women’s work is equal to 6 boys’ work. A boy can finish the work in 60 days. In how many days can the work be finished by a man and a woman together?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFCalculation:
According to the question,
4M = 6W
⇒ M : W = 3 : 2
Again, 4W = 6B
⇒ W : B = 3 : 2
So, M : W : B = 9 : 6 : 4
A boy can finish the work in 60 days, so total work = (60 × 4) = 240 unit
Now, a man and a woman together can do the work in 240/15 = 16 days
∴ The correct answer is 16 days
Last updated on Jul 19, 2025
-> The SSC CGL Notification 2025 has been announced for 14,582 vacancies of various Group B and C posts across central government departments.
-> CSIR NET City Intimation Slip 2025 has been released @csirnet.nta.ac.in.
-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025 in multiple shifts.
-> Aspirants should visit the official website @ssc.gov.in 2025 regularly for CGL Exam updates and latest announcements.
-> Candidates had filled out the SSC CGL Application Form from 9 June to 5 July, 2025. Now, 20 lakh+ candidates will be writing the SSC CGL 2025 Exam on the scheduled exam date. Download SSC Calendar 2025-25!
-> In the SSC CGL 2025 Notification, vacancies for two new posts, namely, "Section Head" and "Office Superintendent" have been announced.
-> Candidates can refer to the CGL Syllabus for a better understanding of the exam structure and pattern.
-> The CGL Eligibility is a bachelor’s degree in any discipline, with the age limit varying from post to post.
-> The SSC CGL Salary structure varies by post, with entry-level posts starting at Pay Level-4 (Rs. 25,500 to 81,100/-) and going up to Pay Level-7 (Rs. 44,900 to 1,42,400/-).
-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.