Download Solution PDF30 men can complete a work in 16 days. Six days after they started working, 15 more men joined them. How many days will they now take to complete the remaining work?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFCalculation:
Total Work = 30 × 16 = 480 units
Work done in 1 day =
Work done in 6 days =
Remaining work = 1 -
Work remaining =
Total men = 30 + 15 = 45
Days required =
∴
Last updated on Jul 4, 2025
-> UP Police Constable 2025 Notification will be released for 19220 vacancies by July End 2025.
-> Check UPSC Prelims Result 2025, UPSC IFS Result 2025, UPSC Prelims Cutoff 2025, UPSC Prelims Result 2025 Name Wise & Rollno. Wise
-> UPPRPB Constable application window is expected to open in July 2025.
-> UP Constable selection is based on Written Examination, Document Verification, Physical Measurements Test, and Physical Efficiency Test.
-> Candidates can attend the UP Police Constable and can check the UP Police Constable Previous Year Papers. Also, check UP Police Constable Exam Analysis.